New Wismar-Mackenzie bridge 97% complete – ministry

New Wismar-Mackenzie bridge 97% complete - ministry
March 9, 2026

LATEST NEWS

New Wismar-Mackenzie bridge 97% complete – ministry

The Ministry of Public Works today announced that physical works on the New Wismar-Mackenzie Bridge in Linden, Region Ten, are now 97% complete. This update was provided to the Minister of Public Works, Juan Edghill, on Friday during a visit to the project site.

A release from the ministry said that the Minister held a multi-stakeholder meeting which included technical staff from the Ministry, contractors China Railway Construction (Caribbean) Company Ltd. and GuyCo Construction Inc., and the consultancy firm, Politecnica.

During the visit,  Edghill and representatives from various stakeholders conducted an onsite walkthrough of the 233-metre-long concrete bridge, where concrete placement is currently at 97%. The walkthrough also included an inspection of the secondary connections leading to and from the bridge.

A project debriefing revealed that works on the Western End (Wismar side)—specifically the West Watooka Connector and Dacoura Haul Roads—are 33% complete. For these two main arteries, subgrade preparation, subbase, crusher run base, and curbing are 100% finished. The release said that the foundation works for the roundabout are also 100% complete, with curbing at 50%. Additionally, work on the Burnham Drive approach is advancing, with subsurface works at 38%, curbing at 39%, and culvert works currently underway.

Works on the Eastern End of the bridge are 27% complete, accounting for foundation and retaining structures. At the time of the visit, 3,750 prefabricated vertical drains had been installed and geotextiles laid, with the contractor currently placing white sand and crushed stone as part of the subsurface works.

A new culvert at the Washer Pond Road approach at Noitgedacht has been installed, and construction is under way for the retaining wall of the main embankment. Excavation and geotextile installation are complete, with backfilling ongoing to prepare for final surfacing.

The project remains on track to be fully operational by June 2026, pending the completion of the connector roads, the release said. When finished, the toll-free crossing will feature two barrier-separated pedestrian walkways, modern lighting, and two new roundabouts on both the eastern and western sides of the bridge.

Share this post:

POLL

Who Will Vote For?

Other

Republican

Democrat

RECENT NEWS

Gas station bomber confesses - Kaieteur News

Gas station bomber confesses – Kaieteur News

Bartica man fined $250k for drunk, dangerous driving

Bartica man fined $250k for drunk, dangerous driving

Expanded services for East Coast residents as Demerara Bank opens new BV branch

Expanded services for East Coast residents as Demerara Bank opens new BV branch

Dynamic Country URL Go to Country Info Page